Pace Engineering was engaged to manufacture new, and repair existing equipment, for a planned plant overhaul at York Road, Stratford.
A new hopper bin and vibrating grizzlie screen were made at the Pace Fabrication workshops. Eccentric flywheels and bearing housings were later added in a design modification upgrade.
The Machine shop manufactured a new rotating shaft assembly and spacer from which to mount the flywheels prior to assembly. They also refurbished a hydraulic tube and piston in the process.
A pair of fully synchronized twin 450KVA gensets were supplied by Pace Power and Air for primary power.
Pace Engineering worked collaboratively with all departments of its business to provide multi-faceted engineering services with guaranteed satisfaction.